RISK – Workers inside Rail Corridor do not revise controls as environment changes, resulting in serious incident (WHS) and / or Category A notifiable occurrence (RSNL)
The review of the worksite protection plan should be performed in consultation with supervisor/superintendent and relevant stakeholders.
Where task planning impacts worksite protection arrangement, those changes must be reviewed for their impact on the worksite protection arrangements.
If any changes are required to the worksite protection plan, these changes must be documented in the revised plan and communicated to all relevant personnel, before works can commence or resume.
Related GMRs
10.5 Implement controls identified in the work protection plan prior to commence work
Related Procedures / Forms
Relevant Rail Infrastructure Manager’s Network Rules and Procedures