10.E Review and revise the worksite protection plan if required and when changes affect the worksite protection controls

RISK – Workers inside Rail Corridor do not revise controls as environment changes, resulting in serious incident (WHS) and / or Category A notifiable occurrence (RSNL)

The review of the worksite protection plan should be performed in consultation with supervisor/superintendent and relevant stakeholders.

 

 

 

Where task planning impacts worksite protection arrangement, those changes must be reviewed for their impact on the worksite protection arrangements.

 

 

If any changes are required to the worksite protection plan, these changes must be documented in the revised plan and communicated to all relevant personnel, before works can commence or resume.

 

 

 

 

 

 

Related GMRs

10.3 Ensure the qualified work in charge undertakes a worksite protection site specific risk assessment

10.4 Develop a Worksite Protection Plan to manage the risks identified in the worksite protection site specific risk assessment

10.5 Implement controls identified in the work protection plan prior to commence work

10.C Confirm with the qualified worker in charge that the worksite protection controls are in place prior to commencing work


Related Procedures / Forms

Relevant Rail Infrastructure Manager’s Network Rules and Procedures


© John Holland Pty Ltd.

GMRs

  • Home
  • About the GMRs & this site
    • What are the GMRs?
    • What do the GMRs include?
    • Implementing the GMRs
    • Our GMR Videos
  • 1. Traffic, Plant & People
    • 1.1 Separating vehicles
    • 1.2 Overhead services and structures
    • 1.3 Pedestrian Separation
    • 1.4 Working in Operating Zones
    • 1.5 Fit for purpose plant
    • 1.6 Plant Modification
    • 1.A Licence and Verification
    • 1.B Road and rail rules
    • 1.C Seating position & seat-belts
    • 1.D Spotters
    • 1.E Operating zone permissions
    • 1.F Positioning plant
  • 2. Excavation & Trenching
    • 2.1 Excavation design
    • 2.2 Services and Structural Drawings
    • 2.3 Zone of Influence
    • 2.4 Barricading and Signage
    • 2.5 Services within 5m
    • 2.6 Tunnelling Controls
    • 2.A Positive Service Location
    • 2.B Access requirements
    • 2.C Safe Approach Distances
    • 2.D Excavation inspections
    • 2.E Preventing unauthorised access
  • 3. Lifting Operations
    • 3.1 Lift Competencies
    • 3.2 Lift Designer
    • 3.3 Ground Bearing Capacities
    • 3.4 Inspections & Maintenance
    • 3.5 Mobile plant load limits
    • 3.6 Lifting site inspection
    • 3.A Pre-Start Inspections
    • 3.B Mobile Plant used for lift
    • 3.C Exclusion zones
    • 3.D Suspended Loads
    • 3.E Competent Person(s)
  • 4. Electrical Safety
    • 4.1 Licences for Electrical Work
    • 4.2 Live electrical systems
    • 4.3 Safe System of Work
    • 4.4 Protective devices
    • 4.A Treat as Live
    • 4.B Legislative Requirements
    • 4.C Safe working distance
    • 4.D Electrical Supply Panels
  • 5. Work at Height
    • 5.1 Fall from height
    • 5.2 Falling objects
    • 5.3 Penetrations, shafts & risers
    • 5.4 EWP Protection Devices
    • 5.5 Grid Mesh / Chequer Plates
    • 5.A Barricades and exclusion zones
    • 5.B Overloading & adjustments
    • 5.C Harnesses
    • 5.D Installing roof sheeting
    • 5.E WAH Training
    • 5.F Accessing vehicles
  • 6. Wellbeing
    • 6.1 Wellbeing Risk Management
    • 6.2 Work rosters & Wellbeing programs
    • 6.3 Facility maintenance
    • 6.4 Occupational Hygiene
    • 6.5 AOD monitoring
    • 6.6 Wellbeing Champions
    • 6.A Be fit for work
    • 6.B Notify if unfit
    • 6.C Supportive work environment
    • 6.D Wellbeing Training
    • 6.E Know your Champions
    • 6.F Wellbeing Events
  • 7. Temporary Works
    • 7.1 Temporary Works Coordinator
    • 7.2 Temporary Works register
    • 7.3 TW Competencies
    • 7.4 Design Controls
    • 7.5 Temporary Work Protection
    • 7.6 Communication
    • 7.A Installation and Removal
    • 7.B Site validation
    • 7.C Working Load Limits
    • 7.D Inspection Schedule
    • 7.E Alterations
  • 8. Isolation
    • 8.1 Identifying Energy Sources
    • 8.2 Identifying Risks
    • 8.3 Isolations competencies
    • 8.4 Isolation Points
    • 8.5 Identifying Stored Energy
    • 8.A Test before touch
    • 8.B Releasing Stored Energy
    • 8.C Reviewing Isolation Status
    • 8.D Monitoring Isolation Controls
    • 8.E Re-instate guards
    • 8.F Personal Danger Tags/Locks
  • 9. Environmental Management
    • 9.1 Identifying risks
    • 9.2 Approvals/Licences/Permits
    • 9.3 Implementing Controls
    • 9.4 Identifying heritage, flora and fauna
    • 9.5 Minimising Resource Use
    • 9.6 Spoil and waste classification
    • 9.A Sensitive areas & boundaries
    • 9.B Dust, noise & vibration
    • 9.C Waste & hazardous substances
    • 9.D Maintaining / reviewing controls
    • 9.E Environmental findings
    • 9.F Water discharge
  • 10. Work on Rail
    • 10.1 Rail Competencies
    • 10.2 Qualified worker responsibilities
    • 10.3 Worksite Protection Risk Assessment
    • 10.4 Worksite Protection Plan
    • 10.5 Implement controls
    • 10.A Rail compliant PPE
    • 10.B Pre-work brief
    • 10.C Confirm protection controls
    • 10.D Network rules & safety instructions
    • 10.E Review Worksite Protection Plan
    • 10.F Rail certification
  • Knowledge Requirements
  • Glossary
Toggle