2. Excavation & Trenching

2.3 Plan the location of plant, equipment, vehicles and stored materials (including soil) to ensure they remain outside the zone of influence

RISK – Ground collapse and engulfment

An excavation’s zone of influence refers to the volume of soil around an excavation that can be affected by any external load.  The zone is usually measured as 45 degrees out from the bottom of an excavation.

 

 

 

Whilst the zone of influence is usually measured as 45 degrees out from the bottom of an excavation, this may change depending on the soil type and weight of the material/vehicle.

 

 

Mechanical plant, vehicles, storage of materials (including excavated material) or any other heavy loads must not be located in the zone of influence of an excavation as this will place additional load onto that area.

 

As a general rule, it is best practice to place all loads and barricades at least 1m back from the zone of influence.

Excavation Safety Guide. Worksafe New Zealand

 

The zone of influence will depend on the ground conditions.  It is the zone in which there may be an influence on the excavation, including possible ground collapse.

 

Where the ground around the excavation may be affected by any external load, a Geotechnical Engineer must determine whether protective systems (as per GMR 2.1) needs to be designed and installed to accommodate the additional load.

 

If spoil is placed close to an excavation due to obstructions like fences, buildings or trees, the weight of the spoil may overload the excavation face and cause the excavation to collapse.

If materials cannot be placed outside the zone of influence due to limited space, a ground support (or protective) system must be designed and installed to carry the additional load.

 

Model Code of Practice for Excavation Work. Safe Work Australia

 

Consider also, the excavations zone of influence on the stability of any nearby structures and make sure the excavation does not remove any ground support from these structures

 

Shafts

In regard to shafts, consideration must also be given to additional loadings such as:

  • barriers/edge protection on the shaft top
  • cranage on the shaft or excavation side walls
  • construction space-proofing to ensure loads can pass freely

Any further loads imposed on these systems (such as man riders and hoists) must be factored into the overall design.

 

 

Refer to the Excavation Material and Loads near Excavations section of the Excavation and Trenching Procedure (linked below) for further information

 

 

Related GMRs
2.1 Assess excavation design requirements and implement appropriate protective systems
2.E Maintain barricading and signage requirements to prevent unauthorised access to excavations

 

Related Procedures / Forms
Excavation and Trenching Procedure


© John Holland Pty Ltd.

GMRs

  • Home
  • About the GMRs & this site
    • What are the GMRs?
    • What do the GMRs include?
    • Implementing the GMRs
    • Our GMR Videos
  • 1. Traffic, Plant & People
    • 1.1 Separating vehicles
    • 1.2 Overhead services and structures
    • 1.3 Pedestrian Separation
    • 1.4 Working in Operating Zones
    • 1.5 Fit for purpose plant
    • 1.6 Plant Modification
    • 1.A Licence and Verification
    • 1.B Road and rail rules
    • 1.C Seating position & seat-belts
    • 1.D Spotters
    • 1.E Operating zone permissions
    • 1.F Positioning plant
  • 2. Excavation & Trenching
    • 2.1 Excavation design
    • 2.2 Services and Structural Drawings
    • 2.3 Zone of Influence
    • 2.4 Barricading and Signage
    • 2.5 Services within 5m
    • 2.6 Tunnelling Controls
    • 2.A Positive Service Location
    • 2.B Access requirements
    • 2.C Safe Approach Distances
    • 2.D Excavation inspections
    • 2.E Preventing unauthorised access
  • 3. Lifting Operations
    • 3.1 Lift Competencies
    • 3.2 Lift Designer
    • 3.3 Ground Bearing Capacities
    • 3.4 Inspections & Maintenance
    • 3.5 Mobile plant load limits
    • 3.6 Lifting site inspection
    • 3.A Pre-Start Inspections
    • 3.B Mobile Plant used for lift
    • 3.C Exclusion zones
    • 3.D Suspended Loads
    • 3.E Competent Person(s)
  • 4. Electrical Safety
    • 4.1 Licences for Electrical Work
    • 4.2 Live electrical systems
    • 4.3 Safe System of Work
    • 4.4 Protective devices
    • 4.A Treat as Live
    • 4.B Legislative Requirements
    • 4.C Safe working distance
    • 4.D Electrical Supply Panels
  • 5. Work at Height
    • 5.1 Fall from height
    • 5.2 Falling objects
    • 5.3 Penetrations, shafts & risers
    • 5.4 EWP Protection Devices
    • 5.5 Grid Mesh / Chequer Plates
    • 5.A Barricades and exclusion zones
    • 5.B Overloading & adjustments
    • 5.C Harnesses
    • 5.D Installing roof sheeting
    • 5.E WAH Training
    • 5.F Accessing vehicles
  • 6. Wellbeing
    • 6.1 Wellbeing Risk Management
    • 6.2 Work rosters & Wellbeing programs
    • 6.3 Facility maintenance
    • 6.4 Occupational Hygiene
    • 6.5 AOD monitoring
    • 6.6 Wellbeing Champions
    • 6.A Be fit for work
    • 6.B Notify if unfit
    • 6.C Supportive work environment
    • 6.D Wellbeing Training
    • 6.E Know your Champions
    • 6.F Wellbeing Events
  • 7. Temporary Works
    • 7.1 Temporary Works Coordinator
    • 7.2 Temporary Works register
    • 7.3 TW Competencies
    • 7.4 Design Controls
    • 7.5 Temporary Work Protection
    • 7.6 Communication
    • 7.A Installation and Removal
    • 7.B Site validation
    • 7.C Working Load Limits
    • 7.D Inspection Schedule
    • 7.E Alterations
  • 8. Isolation
    • 8.1 Identifying Energy Sources
    • 8.2 Identifying Risks
    • 8.3 Isolations competencies
    • 8.4 Isolation Points
    • 8.5 Identifying Stored Energy
    • 8.A Test before touch
    • 8.B Releasing Stored Energy
    • 8.C Reviewing Isolation Status
    • 8.D Monitoring Isolation Controls
    • 8.E Re-instate guards
    • 8.F Personal Danger Tags/Locks
  • 9. Environmental Management
    • 9.1 Identifying risks
    • 9.2 Approvals/Licences/Permits
    • 9.3 Implementing Controls
    • 9.4 Identifying heritage, flora and fauna
    • 9.5 Minimising Resource Use
    • 9.6 Spoil and waste classification
    • 9.A Sensitive areas & boundaries
    • 9.B Dust, noise & vibration
    • 9.C Waste & hazardous substances
    • 9.D Maintaining / reviewing controls
    • 9.E Environmental findings
    • 9.F Water discharge
  • 10. Work on Rail
    • 10.1 Rail Competencies
    • 10.2 Qualified worker responsibilities
    • 10.3 Worksite Protection Risk Assessment
    • 10.4 Worksite Protection Plan
    • 10.5 Implement controls
    • 10.A Rail compliant PPE
    • 10.B Pre-work brief
    • 10.C Confirm protection controls
    • 10.D Network rules & safety instructions
    • 10.E Review Worksite Protection Plan
    • 10.F Rail certification
  • Knowledge Requirements
  • Glossary