2. Excavation & Trenching

2.D Conduct daily inspections for excavations and trenches greater than 1.5m deep prior to works commencing

RISK – Trench collapse. Engulfment

Excavations and trenches must be inspected at least daily. Tunnelling inspections will be conducted more frequently in line with the Permit to Tunnel.  

 

 

 

The inspection must be conducted by a person who has completed the Excavation and Trenching Awareness Training (linked below) as a minimum.

 

 

Inspections must be conducted more frequently if a rainfall event or any other event could impact ground stability or introduce further hazards.

 

 

If any indication of ground movement is identified (e.g. cracks, undercutting, bulging etc.) or any impacts to adjacent structures are identified, the integrity of the excavation should be reviewed before any work in that area commences.

 

 

Ground conditions encountered in excavations can generally be categorised as one of 3 types:

  • Hard, compact soil
  • Soil liable to crack or crumble, and
  • Loose or running material

Hard, compact soil is often the most hazardous as the face of the excavation can look solid, which can lead in more risks being taken.

With loose or running material, it is obvious that controls are needed from the start and more precautions are taken to prevent collapse.

 

 

The stability of any excavated face depends on the strength of the soil in the face being greater at all times than the stresses it is subjected to.

 

 

The following situations all increase soil stresses in an excavated face, which may lead to failure:

  • Deep cuts and steep slopes
  • Loads placed near the excavation face inside the zone of influence
  • Shock and vibration
  • Water pressure from groundwater
  • Soil saturation

 

 

Those inspecting the excavation should look out for:

  • Fissures or cracks on the excavation face
  • Slumping of material, soil or rock
  • Bulging or heaving of material at the bottom of the excavation wall
  • Sinking at the edge of the trench
  • Pebbles of clumps of dirt rolling down the excavation face

 

 

Types of ground collapse:

 

Excavation Safety Guide. New Zealand

 

 

Inspections for tunnelling / underground works

Ongoing inspections and discussions with the designer will be required throughout the activity to ensure any changes to the ground conditions are promptly identified and addressed.

The inspection regime will be documented within the permit as inspection frequencies are dependent on the design and ground type. The ground types will be categorised by the Designer with the Geotechnical Engineer classifying the ground conditions and allocating the corresponding ground supports required for that ground type.

Example of mapping:

 

 

 

Related GMRs

2.1 Assess excavation design requirements and implement appropriate protective systems

2.3 Plan the location of plant, equipment, vehicles and stored materials (including soil) to ensure they remain outside the zone of influence

2.B Only access an excavation deeper than 1.5m if it has been benched, battered, shored, or signed off by a Geotechnical Engineer

 

Related Procedures / Forms

Excavation and Trenching Procedure

Excavation and Trenching Procedural Awareness Training

Permit to Tunnel


© John Holland Pty Ltd.

GMRs

  • Home
  • About the GMRs & this site
    • What are the GMRs?
    • What do the GMRs include?
    • Implementing the GMRs
    • Our GMR Videos
  • 1. Traffic, Plant & People
    • 1.1 Separating vehicles
    • 1.2 Overhead services and structures
    • 1.3 Pedestrian Separation
    • 1.4 Working in Operating Zones
    • 1.5 Fit for purpose plant
    • 1.6 Plant Modification
    • 1.A Licence and Verification
    • 1.B Road and rail rules
    • 1.C Seating position & seat-belts
    • 1.D Spotters
    • 1.E Operating zone permissions
    • 1.F Positioning plant
  • 2. Excavation & Trenching
    • 2.1 Excavation design
    • 2.2 Services and Structural Drawings
    • 2.3 Zone of Influence
    • 2.4 Barricading and Signage
    • 2.5 Services within 5m
    • 2.6 Tunnelling Controls
    • 2.A Positive Service Location
    • 2.B Access requirements
    • 2.C Safe Approach Distances
    • 2.D Excavation inspections
    • 2.E Preventing unauthorised access
  • 3. Lifting Operations
    • 3.1 Lift Competencies
    • 3.2 Lift Designer
    • 3.3 Ground Bearing Capacities
    • 3.4 Inspections & Maintenance
    • 3.5 Mobile plant load limits
    • 3.6 Lifting site inspection
    • 3.A Pre-Start Inspections
    • 3.B Mobile Plant used for lift
    • 3.C Exclusion zones
    • 3.D Suspended Loads
    • 3.E Competent Person(s)
  • 4. Electrical Safety
    • 4.1 Licences for Electrical Work
    • 4.2 Live electrical systems
    • 4.3 Safe System of Work
    • 4.4 Protective devices
    • 4.A Treat as Live
    • 4.B Legislative Requirements
    • 4.C Safe working distance
    • 4.D Electrical Supply Panels
  • 5. Work at Height
    • 5.1 Fall from height
    • 5.2 Falling objects
    • 5.3 Penetrations, shafts & risers
    • 5.4 EWP Protection Devices
    • 5.5 Grid Mesh / Chequer Plates
    • 5.A Barricades and exclusion zones
    • 5.B Overloading & adjustments
    • 5.C Harnesses
    • 5.D Installing roof sheeting
    • 5.E WAH Training
    • 5.F Accessing vehicles
  • 6. Wellbeing
    • 6.1 Wellbeing Risk Management
    • 6.2 Work rosters & Wellbeing programs
    • 6.3 Facility maintenance
    • 6.4 Occupational Hygiene
    • 6.5 AOD monitoring
    • 6.6 Wellbeing Champions
    • 6.A Be fit for work
    • 6.B Notify if unfit
    • 6.C Supportive work environment
    • 6.D Wellbeing Training
    • 6.E Know your Champions
    • 6.F Wellbeing Events
  • 7. Temporary Works
    • 7.1 Temporary Works Coordinator
    • 7.2 Temporary Works register
    • 7.3 TW Competencies
    • 7.4 Design Controls
    • 7.5 Temporary Work Protection
    • 7.6 Communication
    • 7.A Installation and Removal
    • 7.B Site validation
    • 7.C Working Load Limits
    • 7.D Inspection Schedule
    • 7.E Alterations
  • 8. Isolation
    • 8.1 Identifying Energy Sources
    • 8.2 Identifying Risks
    • 8.3 Isolations competencies
    • 8.4 Isolation Points
    • 8.5 Identifying Stored Energy
    • 8.A Test before touch
    • 8.B Releasing Stored Energy
    • 8.C Reviewing Isolation Status
    • 8.D Monitoring Isolation Controls
    • 8.E Re-instate guards
    • 8.F Personal Danger Tags/Locks
  • 9. Environmental Management
    • 9.1 Identifying risks
    • 9.2 Approvals/Licences/Permits
    • 9.3 Implementing Controls
    • 9.4 Identifying heritage, flora and fauna
    • 9.5 Minimising Resource Use
    • 9.6 Spoil and waste classification
    • 9.A Sensitive areas & boundaries
    • 9.B Dust, noise & vibration
    • 9.C Waste & hazardous substances
    • 9.D Maintaining / reviewing controls
    • 9.E Environmental findings
    • 9.F Water discharge
  • 10. Work on Rail
    • 10.1 Rail Competencies
    • 10.2 Qualified worker responsibilities
    • 10.3 Worksite Protection Risk Assessment
    • 10.4 Worksite Protection Plan
    • 10.5 Implement controls
    • 10.A Rail compliant PPE
    • 10.B Pre-work brief
    • 10.C Confirm protection controls
    • 10.D Network rules & safety instructions
    • 10.E Review Worksite Protection Plan
    • 10.F Rail certification
  • Knowledge Requirements
  • Glossary