3. Lifting Operations

3.1 All lifting operations must be planned, managed and conducted by a competent person

RISK – Lift Failure

Refer to the Lifting Operations Competency Matrix & the Lifting Operations Procedure for lifting competencies.

 

 

 

Anyone undertaking high risk work must have the relevant high risk work licence and be verified as competent in accordance with the Verification of Competency (VOC) Procedure (linked below).

 

 

Lift Plans must be developed, checked and authorised in accordance with the Lifting Planning Matrix.

 

 

Any changes to lifting operations must trigger a review of the Lift Plan by the Lift Planner to determine whether the lift requires re-categorisation.

 

 

Use the Lift Planning Matrix to determine whether the lift is a critical, medium or low risk lift.  Factors such as the weight of the load, multiple hoists/load share, rigging requirements, lifting configuration and ground conditions will help determine the risk level.

 

Lift Planning Matrix

 

 

Mandatory competencies for a Lift Designer:

  • Workplace Induction
  • Lifting Operation Procedure familiarisation training
  • Lift Designer Training
  • Lift Designer – Level 2 – Competency Assessment (Theory)
  • Mentoring with a Heavy Lift Specialist
  • Demonstrated experience in the lift design process (Practical)
  • Workplace Manager Approval
  • Competency letter issued

 

 

Mandatory competencies for a Heavy Lift Specialist:

  • Workplace Induction
  • Lifting Operation Procedure familiarisation training
  • Lift Designer Training
  • Lift Designer – Level 2 – Competency Assessment (Theory)
  • Experience in the lift design process, use of crane specialist software and AutoCAD
  • Minimum 8 years previous relevant crane, rigging & transport experience
  • Regional General Manager Approval
  • Competency letter issued

 

 

Click here to see a list of high risk work licences and classes of high risk work.

SafeWork NSW

 

 

A Verification of Competency is a method used to determine the ability of an individual (both JH and subcontractors) to competently perform high risk work or operate an item of plant or equipment safely.  This John Holland requirement is in addition to the attainment of any high risk work licence and/or other qualifications.

 

 

Related GMRs

1.A Only operate plant, machinery or vehicles, if you hold the applicable licence, have been verified as competent (if required), and have completed a daily pre-start check of the equipment

3.E Do not undertake any lifting operations unless you are trained, qualified and competent to do so

 

Related Procedures / Forms

Lifting Operations Procedure

Verification of Competency Procedure


© John Holland Pty Ltd.

GMRs

  • Home
  • About the GMRs & this site
    • What are the GMRs?
    • What do the GMRs include?
    • Implementing the GMRs
    • Our GMR Videos
  • 1. Traffic, Plant & People
    • 1.1 Separating vehicles
    • 1.2 Overhead services and structures
    • 1.3 Pedestrian Separation
    • 1.4 Working in Operating Zones
    • 1.5 Fit for purpose plant
    • 1.6 Plant Modification
    • 1.A Licence and Verification
    • 1.B Road and rail rules
    • 1.C Seating position & seat-belts
    • 1.D Spotters
    • 1.E Operating zone permissions
    • 1.F Positioning plant
  • 2. Excavation & Trenching
    • 2.1 Excavation design
    • 2.2 Services and Structural Drawings
    • 2.3 Zone of Influence
    • 2.4 Barricading and Signage
    • 2.5 Services within 5m
    • 2.6 Tunnelling Controls
    • 2.A Positive Service Location
    • 2.B Access requirements
    • 2.C Safe Approach Distances
    • 2.D Excavation inspections
    • 2.E Preventing unauthorised access
  • 3. Lifting Operations
    • 3.1 Lift Competencies
    • 3.2 Lift Designer
    • 3.3 Ground Bearing Capacities
    • 3.4 Inspections & Maintenance
    • 3.5 Mobile plant load limits
    • 3.6 Lifting site inspection
    • 3.A Pre-Start Inspections
    • 3.B Mobile Plant used for lift
    • 3.C Exclusion zones
    • 3.D Suspended Loads
    • 3.E Competent Person(s)
  • 4. Electrical Safety
    • 4.1 Licences for Electrical Work
    • 4.2 Live electrical systems
    • 4.3 Safe System of Work
    • 4.4 Protective devices
    • 4.A Treat as Live
    • 4.B Legislative Requirements
    • 4.C Safe working distance
    • 4.D Electrical Supply Panels
  • 5. Work at Height
    • 5.1 Fall from height
    • 5.2 Falling objects
    • 5.3 Penetrations, shafts & risers
    • 5.4 EWP Protection Devices
    • 5.5 Grid Mesh / Chequer Plates
    • 5.A Barricades and exclusion zones
    • 5.B Overloading & adjustments
    • 5.C Harnesses
    • 5.D Installing roof sheeting
    • 5.E WAH Training
    • 5.F Accessing vehicles
  • 6. Wellbeing
    • 6.1 Wellbeing Risk Management
    • 6.2 Work rosters & Wellbeing programs
    • 6.3 Facility maintenance
    • 6.4 Occupational Hygiene
    • 6.5 AOD monitoring
    • 6.6 Wellbeing Champions
    • 6.A Be fit for work
    • 6.B Notify if unfit
    • 6.C Supportive work environment
    • 6.D Wellbeing Training
    • 6.E Know your Champions
    • 6.F Wellbeing Events
  • 7. Temporary Works
    • 7.1 Temporary Works Coordinator
    • 7.2 Temporary Works register
    • 7.3 TW Competencies
    • 7.4 Design Controls
    • 7.5 Temporary Work Protection
    • 7.6 Communication
    • 7.A Installation and Removal
    • 7.B Site validation
    • 7.C Working Load Limits
    • 7.D Inspection Schedule
    • 7.E Alterations
  • 8. Isolation
    • 8.1 Identifying Energy Sources
    • 8.2 Identifying Risks
    • 8.3 Isolations competencies
    • 8.4 Isolation Points
    • 8.5 Identifying Stored Energy
    • 8.A Test before touch
    • 8.B Releasing Stored Energy
    • 8.C Reviewing Isolation Status
    • 8.D Monitoring Isolation Controls
    • 8.E Re-instate guards
    • 8.F Personal Danger Tags/Locks
  • 9. Environmental Management
    • 9.1 Identifying risks
    • 9.2 Approvals/Licences/Permits
    • 9.3 Implementing Controls
    • 9.4 Identifying heritage, flora and fauna
    • 9.5 Minimising Resource Use
    • 9.6 Spoil and waste classification
    • 9.A Sensitive areas & boundaries
    • 9.B Dust, noise & vibration
    • 9.C Waste & hazardous substances
    • 9.D Maintaining / reviewing controls
    • 9.E Environmental findings
    • 9.F Water discharge
  • 10. Work on Rail
    • 10.1 Rail Competencies
    • 10.2 Qualified worker responsibilities
    • 10.3 Worksite Protection Risk Assessment
    • 10.4 Worksite Protection Plan
    • 10.5 Implement controls
    • 10.A Rail compliant PPE
    • 10.B Pre-work brief
    • 10.C Confirm protection controls
    • 10.D Network rules & safety instructions
    • 10.E Review Worksite Protection Plan
    • 10.F Rail certification
  • Knowledge Requirements
  • Glossary