5. Work at Height

5.C Only use a harness as a primary control if approved by the BU Operations Manager and a more effective control is not reasonably practical

RISK – Falls from height

If a harness is required, raise a work at height permit and submit to the BU Operations Manager for approval.

 

 

 

Use the hierarchy of control (HOC) to ensure the most effective control is implemented and minimise the use of a harness as a primary fall protection control where possible.  See guidance for GMR 5.1 for the work at height hierarchy.

 

 

A work at height permit must be completed when a risk assessment has determined that:

  • A more effective controls is not reasonably practical
  • A level 3 or 4 work at height control is required (see GMR 5.1)
  • A worker is required to wear a fall restraint / arrest harness as a primary means of fall protection

 

 

Once completed, the permit is endorsed by the Workplace Manager and Workplace Safety Professional and submitted to the BU Operations Manager for review and approval along with the following documents:

  • Task risk assessment
  • Initial review of the task risk assessment
  • Copy of the worker qualifications
  • Completed harness and lanyard inspection checklist

The work at height permit is the only permit that requires an approver external to the project.

 

 

 

 

Anchorage Points
All anchorage points must be designed and certified by a qualified person.

All anchorage points must be installed by a trained person and regularly inspected prior to use by a competent person.

The building / structure and anchorage points are to be assessed by an engineer, unless it is clear to a competent person that the anchorage system is structurally adequate. This includes verifying the system has been appropriately installed or has the necessary approvals in place prior to starting work.

 

 

 

 

Lanyards

It is best practice for lanyards to be obtained from the same manufacturer as the harness to ensure compatibility between components. Mismatches can result in the "roll out" of the hook from the "D" ring.

Lanyard hooks are not be connected directly to the static line.  A karabiner must be used.

The harness and the lanyard must be rated to support the weight of a person during a fall. Harnesses must support a minimum body weight of approximately 120kg. 

 

The harness and lanyard manufacturing weight specifications must be checked against the individual using those items prior to donning them and working at height to ensure that the harness and lanyard specifications are appropriate for the person's body weight.

 

 

Related GMRs

5.1 Identify all tasks that present a potential fall from height of a person and implement appropriate control measures

 

Related Procedures / Forms

Work at Height Procedure

Work at Height Permit


© John Holland Pty Ltd.

GMRs

  • Home
  • About the GMRs & this site
    • What are the GMRs?
    • What do the GMRs include?
    • Implementing the GMRs
    • Our GMR Videos
  • 1. Traffic, Plant & People
    • 1.1 Separating vehicles
    • 1.2 Overhead services and structures
    • 1.3 Pedestrian Separation
    • 1.4 Working in Operating Zones
    • 1.5 Fit for purpose plant
    • 1.6 Plant Modification
    • 1.A Licence and Verification
    • 1.B Road and rail rules
    • 1.C Seating position & seat-belts
    • 1.D Spotters
    • 1.E Operating zone permissions
    • 1.F Positioning plant
  • 2. Excavation & Trenching
    • 2.1 Excavation design
    • 2.2 Services and Structural Drawings
    • 2.3 Zone of Influence
    • 2.4 Barricading and Signage
    • 2.5 Services within 5m
    • 2.6 Tunnelling Controls
    • 2.A Positive Service Location
    • 2.B Access requirements
    • 2.C Safe Approach Distances
    • 2.D Excavation inspections
    • 2.E Preventing unauthorised access
  • 3. Lifting Operations
    • 3.1 Lift Competencies
    • 3.2 Lift Designer
    • 3.3 Ground Bearing Capacities
    • 3.4 Inspections & Maintenance
    • 3.5 Mobile plant load limits
    • 3.6 Lifting site inspection
    • 3.A Pre-Start Inspections
    • 3.B Mobile Plant used for lift
    • 3.C Exclusion zones
    • 3.D Suspended Loads
    • 3.E Competent Person(s)
  • 4. Electrical Safety
    • 4.1 Licences for Electrical Work
    • 4.2 Live electrical systems
    • 4.3 Safe System of Work
    • 4.4 Protective devices
    • 4.A Treat as Live
    • 4.B Legislative Requirements
    • 4.C Safe working distance
    • 4.D Electrical Supply Panels
  • 5. Work at Height
    • 5.1 Fall from height
    • 5.2 Falling objects
    • 5.3 Penetrations, shafts & risers
    • 5.4 EWP Protection Devices
    • 5.5 Grid Mesh / Chequer Plates
    • 5.A Barricades and exclusion zones
    • 5.B Overloading & adjustments
    • 5.C Harnesses
    • 5.D Installing roof sheeting
    • 5.E WAH Training
    • 5.F Accessing vehicles
  • 6. Wellbeing
    • 6.1 Wellbeing Risk Management
    • 6.2 Work rosters & Wellbeing programs
    • 6.3 Facility maintenance
    • 6.4 Occupational Hygiene
    • 6.5 AOD monitoring
    • 6.6 Wellbeing Champions
    • 6.A Be fit for work
    • 6.B Notify if unfit
    • 6.C Supportive work environment
    • 6.D Wellbeing Training
    • 6.E Know your Champions
    • 6.F Wellbeing Events
  • 7. Temporary Works
    • 7.1 Temporary Works Coordinator
    • 7.2 Temporary Works register
    • 7.3 TW Competencies
    • 7.4 Design Controls
    • 7.5 Temporary Work Protection
    • 7.6 Communication
    • 7.A Installation and Removal
    • 7.B Site validation
    • 7.C Working Load Limits
    • 7.D Inspection Schedule
    • 7.E Alterations
  • 8. Isolation
    • 8.1 Identifying Energy Sources
    • 8.2 Identifying Risks
    • 8.3 Isolations competencies
    • 8.4 Isolation Points
    • 8.5 Identifying Stored Energy
    • 8.A Test before touch
    • 8.B Releasing Stored Energy
    • 8.C Reviewing Isolation Status
    • 8.D Monitoring Isolation Controls
    • 8.E Re-instate guards
    • 8.F Personal Danger Tags/Locks
  • 9. Environmental Management
    • 9.1 Identifying risks
    • 9.2 Approvals/Licences/Permits
    • 9.3 Implementing Controls
    • 9.4 Identifying heritage, flora and fauna
    • 9.5 Minimising Resource Use
    • 9.6 Spoil and waste classification
    • 9.A Sensitive areas & boundaries
    • 9.B Dust, noise & vibration
    • 9.C Waste & hazardous substances
    • 9.D Maintaining / reviewing controls
    • 9.E Environmental findings
    • 9.F Water discharge
  • 10. Work on Rail
    • 10.1 Rail Competencies
    • 10.2 Qualified worker responsibilities
    • 10.3 Worksite Protection Risk Assessment
    • 10.4 Worksite Protection Plan
    • 10.5 Implement controls
    • 10.A Rail compliant PPE
    • 10.B Pre-work brief
    • 10.C Confirm protection controls
    • 10.D Network rules & safety instructions
    • 10.E Review Worksite Protection Plan
    • 10.F Rail certification
  • Knowledge Requirements
  • Glossary