7. Temporary Works

7.5 Protect temporary works from accidental impact through physical means or through the provision of suitable impact loading in the design

RISK – Damage to Temporary Work and/or Temporary Work failure

Physical protection may include erecting physical barricading around temporary works. A suitable impact allowance in the design may be in the form of providing an impact point load in accordance with the relevant Standards.

 

 

 

Damage or impact can be a result of adverse weather conditions or adjacent work practices.

 

Where physical protection is not possible, engineering design controls must be implemented as a minimum (e.g. including an allowance in design for impact loading or critical member removal).

 

 

 

 

Consider the movement of plant, materials and personnel around the workplace, the nature of adjacent construction activities and the proximity to temporary works.  Methods of protection may include:

  • Clear marking and delineation of zones of travel
  • Demarcation by para-webbing or similar
  • Use of plastic, steel or concrete jersey barriers as appropriate

 

 

Consider the potential hazards caused by adverse weather conditions and provide appropriate protection from the effects of wind, sun, temperature, rain and runoff.

 

 

Related GMRs

N/A


Related Procedures / Forms

Temporary Works Manual

Work at Height Procedure


© John Holland Pty Ltd.

GMRs

  • Home
  • About the GMRs & this site
    • What are the GMRs?
    • What do the GMRs include?
    • Implementing the GMRs
    • Our GMR Videos
  • 1. Traffic, Plant & People
    • 1.1 Separating vehicles
    • 1.2 Overhead services and structures
    • 1.3 Pedestrian Separation
    • 1.4 Working in Operating Zones
    • 1.5 Fit for purpose plant
    • 1.6 Plant Modification
    • 1.A Licence and Verification
    • 1.B Road and rail rules
    • 1.C Seating position & seat-belts
    • 1.D Spotters
    • 1.E Operating zone permissions
    • 1.F Positioning plant
  • 2. Excavation & Trenching
    • 2.1 Excavation design
    • 2.2 Services and Structural Drawings
    • 2.3 Zone of Influence
    • 2.4 Barricading and Signage
    • 2.5 Services within 5m
    • 2.6 Tunnelling Controls
    • 2.A Positive Service Location
    • 2.B Access requirements
    • 2.C Safe Approach Distances
    • 2.D Excavation inspections
    • 2.E Preventing unauthorised access
  • 3. Lifting Operations
    • 3.1 Lift Competencies
    • 3.2 Lift Designer
    • 3.3 Ground Bearing Capacities
    • 3.4 Inspections & Maintenance
    • 3.5 Mobile plant load limits
    • 3.6 Lifting site inspection
    • 3.A Pre-Start Inspections
    • 3.B Mobile Plant used for lift
    • 3.C Exclusion zones
    • 3.D Suspended Loads
    • 3.E Competent Person(s)
  • 4. Electrical Safety
    • 4.1 Licences for Electrical Work
    • 4.2 Live electrical systems
    • 4.3 Safe System of Work
    • 4.4 Protective devices
    • 4.A Treat as Live
    • 4.B Legislative Requirements
    • 4.C Safe working distance
    • 4.D Electrical Supply Panels
  • 5. Work at Height
    • 5.1 Fall from height
    • 5.2 Falling objects
    • 5.3 Penetrations, shafts & risers
    • 5.4 EWP Protection Devices
    • 5.5 Grid Mesh / Chequer Plates
    • 5.A Barricades and exclusion zones
    • 5.B Overloading & adjustments
    • 5.C Harnesses
    • 5.D Installing roof sheeting
    • 5.E WAH Training
    • 5.F Accessing vehicles
  • 6. Wellbeing
    • 6.1 Wellbeing Risk Management
    • 6.2 Work rosters & Wellbeing programs
    • 6.3 Facility maintenance
    • 6.4 Occupational Hygiene
    • 6.5 AOD monitoring
    • 6.6 Wellbeing Champions
    • 6.A Be fit for work
    • 6.B Notify if unfit
    • 6.C Supportive work environment
    • 6.D Wellbeing Training
    • 6.E Know your Champions
    • 6.F Wellbeing Events
  • 7. Temporary Works
    • 7.1 Temporary Works Coordinator
    • 7.2 Temporary Works register
    • 7.3 TW Competencies
    • 7.4 Design Controls
    • 7.5 Temporary Work Protection
    • 7.6 Communication
    • 7.A Installation and Removal
    • 7.B Site validation
    • 7.C Working Load Limits
    • 7.D Inspection Schedule
    • 7.E Alterations
  • 8. Isolation
    • 8.1 Identifying Energy Sources
    • 8.2 Identifying Risks
    • 8.3 Isolations competencies
    • 8.4 Isolation Points
    • 8.5 Identifying Stored Energy
    • 8.A Test before touch
    • 8.B Releasing Stored Energy
    • 8.C Reviewing Isolation Status
    • 8.D Monitoring Isolation Controls
    • 8.E Re-instate guards
    • 8.F Personal Danger Tags/Locks
  • 9. Environmental Management
    • 9.1 Identifying risks
    • 9.2 Approvals/Licences/Permits
    • 9.3 Implementing Controls
    • 9.4 Identifying heritage, flora and fauna
    • 9.5 Minimising Resource Use
    • 9.6 Spoil and waste classification
    • 9.A Sensitive areas & boundaries
    • 9.B Dust, noise & vibration
    • 9.C Waste & hazardous substances
    • 9.D Maintaining / reviewing controls
    • 9.E Environmental findings
    • 9.F Water discharge
  • 10. Work on Rail
    • 10.1 Rail Competencies
    • 10.2 Qualified worker responsibilities
    • 10.3 Worksite Protection Risk Assessment
    • 10.4 Worksite Protection Plan
    • 10.5 Implement controls
    • 10.A Rail compliant PPE
    • 10.B Pre-work brief
    • 10.C Confirm protection controls
    • 10.D Network rules & safety instructions
    • 10.E Review Worksite Protection Plan
    • 10.F Rail certification
  • Knowledge Requirements
  • Glossary