8. Isolation

8.4 All isolation points must be clearly identified, proven isolated, tagged, locked and controlled to prevent inadvertent energisation

RISK – Not isolating effectively

Identifying isolation points can be achieved in a number of ways, including walkthroughs, reviewing piping and instrumentation diagrams and schematics.

 

 

 

Other ways to identify isolation points include:

  • Review operating manuals
  • Talk to operating authorities
  • Obtain assistance from dial before you dig (or equivalent) in identifying buried services, performing visual observations
  • Obtain visual confirmation

 

 

Hazardous materials and energy sources can include:

  • Electricity – mains and stored (UPSs, batteries and capacitators)
  • Fuels
  • Extreme heat or cold
  • Steam
  • Fluids and gases under pressure (water, steam, air, hydraulic fluids)
  • Stored kinetic energy (springs, counterweights, Winch & Cables)
  • Moving machinery
  • Radiation and biological hazards

 

 

The stages of isolating a service are:

 

 

 

 

 

Test for Dead

The Permit Holder, or Isolation Officer on complex sites, must confirm the isolation (zero energy state – electrical, mechanical or potential stored energy) of the equipment.

 

Attach isolation tags and locks

Lock and tag colours stipulated in the John Holland Isolation Procedure are:

  • Personal– red 
  • Permit Holder – purple 
  • Multi-point Isolation – black
  • Isolation Officer – orange
  • Construction zone separation – pink tag and brass lock

Each person in the workgroup must fix their red personal danger lock and tag to the isolation point (single point isolation) or designated lock box (multi-point isolation) as indicated by the isolation permit.

The red Personal danger lock and tag are only to be placed and removed by the person whose name appears on the tag.

 

 

Lock out and tag out equipment

 

 

 

 

 

 

Related GMRs

8.5 Assess machinery for components with potential stored energy under tension or pressure

8.A Test before touch - Test for hazardous material and stored energy prior to breaking containment systems

8.B Release any stored energy prior to opening hoses or vessels under pressure or working with belts and cables under tension


Related Procedures / Forms

Isolation Procedure


© John Holland Pty Ltd.

GMRs

  • Home
  • About the GMRs & this site
    • What are the GMRs?
    • What do the GMRs include?
    • Implementing the GMRs
    • Our GMR Videos
  • 1. Traffic, Plant & People
    • 1.1 Separating vehicles
    • 1.2 Overhead services and structures
    • 1.3 Pedestrian Separation
    • 1.4 Working in Operating Zones
    • 1.5 Fit for purpose plant
    • 1.6 Plant Modification
    • 1.A Licence and Verification
    • 1.B Road and rail rules
    • 1.C Seating position & seat-belts
    • 1.D Spotters
    • 1.E Operating zone permissions
    • 1.F Positioning plant
  • 2. Excavation & Trenching
    • 2.1 Excavation design
    • 2.2 Services and Structural Drawings
    • 2.3 Zone of Influence
    • 2.4 Barricading and Signage
    • 2.5 Services within 5m
    • 2.6 Tunnelling Controls
    • 2.A Positive Service Location
    • 2.B Access requirements
    • 2.C Safe Approach Distances
    • 2.D Excavation inspections
    • 2.E Preventing unauthorised access
  • 3. Lifting Operations
    • 3.1 Lift Competencies
    • 3.2 Lift Designer
    • 3.3 Ground Bearing Capacities
    • 3.4 Inspections & Maintenance
    • 3.5 Mobile plant load limits
    • 3.6 Lifting site inspection
    • 3.A Pre-Start Inspections
    • 3.B Mobile Plant used for lift
    • 3.C Exclusion zones
    • 3.D Suspended Loads
    • 3.E Competent Person(s)
  • 4. Electrical Safety
    • 4.1 Licences for Electrical Work
    • 4.2 Live electrical systems
    • 4.3 Safe System of Work
    • 4.4 Protective devices
    • 4.A Treat as Live
    • 4.B Legislative Requirements
    • 4.C Safe working distance
    • 4.D Electrical Supply Panels
  • 5. Work at Height
    • 5.1 Fall from height
    • 5.2 Falling objects
    • 5.3 Penetrations, shafts & risers
    • 5.4 EWP Protection Devices
    • 5.5 Grid Mesh / Chequer Plates
    • 5.A Barricades and exclusion zones
    • 5.B Overloading & adjustments
    • 5.C Harnesses
    • 5.D Installing roof sheeting
    • 5.E WAH Training
    • 5.F Accessing vehicles
  • 6. Wellbeing
    • 6.1 Wellbeing Risk Management
    • 6.2 Work rosters & Wellbeing programs
    • 6.3 Facility maintenance
    • 6.4 Occupational Hygiene
    • 6.5 AOD monitoring
    • 6.6 Wellbeing Champions
    • 6.A Be fit for work
    • 6.B Notify if unfit
    • 6.C Supportive work environment
    • 6.D Wellbeing Training
    • 6.E Know your Champions
    • 6.F Wellbeing Events
  • 7. Temporary Works
    • 7.1 Temporary Works Coordinator
    • 7.2 Temporary Works register
    • 7.3 TW Competencies
    • 7.4 Design Controls
    • 7.5 Temporary Work Protection
    • 7.6 Communication
    • 7.A Installation and Removal
    • 7.B Site validation
    • 7.C Working Load Limits
    • 7.D Inspection Schedule
    • 7.E Alterations
  • 8. Isolation
    • 8.1 Identifying Energy Sources
    • 8.2 Identifying Risks
    • 8.3 Isolations competencies
    • 8.4 Isolation Points
    • 8.5 Identifying Stored Energy
    • 8.A Test before touch
    • 8.B Releasing Stored Energy
    • 8.C Reviewing Isolation Status
    • 8.D Monitoring Isolation Controls
    • 8.E Re-instate guards
    • 8.F Personal Danger Tags/Locks
  • 9. Environmental Management
    • 9.1 Identifying risks
    • 9.2 Approvals/Licences/Permits
    • 9.3 Implementing Controls
    • 9.4 Identifying heritage, flora and fauna
    • 9.5 Minimising Resource Use
    • 9.6 Spoil and waste classification
    • 9.A Sensitive areas & boundaries
    • 9.B Dust, noise & vibration
    • 9.C Waste & hazardous substances
    • 9.D Maintaining / reviewing controls
    • 9.E Environmental findings
    • 9.F Water discharge
  • 10. Work on Rail
    • 10.1 Rail Competencies
    • 10.2 Qualified worker responsibilities
    • 10.3 Worksite Protection Risk Assessment
    • 10.4 Worksite Protection Plan
    • 10.5 Implement controls
    • 10.A Rail compliant PPE
    • 10.B Pre-work brief
    • 10.C Confirm protection controls
    • 10.D Network rules & safety instructions
    • 10.E Review Worksite Protection Plan
    • 10.F Rail certification
  • Knowledge Requirements
  • Glossary